GASCO – Abudhabi
- Testing and commissioning of 3.3 KV Areva panel.
- Testing and commissioning of AREVA Make LT Panels MCC.
- Testing and commissioning of GUTOR UPS and Battery banks.
- Testing and commissioning of Power Transformers.
- Hi voltage testing of MV cables.
- Testing and commissioning LT motors
- Testing and commissioning of GCP and UCP Controls.
- Testing and Commissioning of SIEMENS Make 3.15 MW Gas turbine and Auxiliaries.
- Testing and commissioning of Nav Aid and Fog alarm systems.
- Modification CT, Control, Protection and Interlock circuit in Existing SIEMNS 3.3KV Panel.
- Testing and commissioning of all electrical hook up between existing and new upgrade.